The Planning and Design of a Fleet Maintenance Facility

Sound theory is crucial, but it depends on a foundation of well-organized practical information. Architect Larry Jacobsen provides some tools.



Last update:
Author: Jacobsen William
Outside the Norfolk, NE Equipment Services Building, currently under construction.

I don’t know what I want, but I’ll know it when I see it,” or “Design me a fleet maintenance facility that’s just like the one in the next community.” These two diverse, but all too common, approaches to facility design ignore the essential first step to building a successful fleet maintenance facility—planning.

This first article in a two-part series will address the planning process for a fleet maintenance facility. The second article will discuss the process of design and development of the construction documents. The articles are based on the Norfolk, Nebraska, Equipment Services Building, which was designed by my company and is currently under construction. The processes of planning and design presented here are not exclusive to fleet maintenance facilities, but work equally well for most types of buildings.

“A Plan is What You Have When You Get Tired of Planning”—Murphy For those unfamiliar with the process of planning, Murphy’s Law of Planning may seem like the norm. But actually, planning is a very objective pre-design process. First, it is a pre-design process that defines the problem for the designer. Designing the project before the design scope is determined leads to inefficiencies, and often a poorly functioning facility.

Interior of the Norfolk, NE Equipment Services Building currently under construction supervised by The Schemmer Associates, Inc..

Planning is also known as facility programming, which is a more accurate description of the pre-design process. Webster’s Dictionary defines programming as “a process leading to the statement of an architectural problem and the requirements to be met in offering a solution.” William Pena, author of Problem Seeking – An Architectural Programming Primer, stated it this way: “If programming is problem seeking, then design is problem solving.” This is probably as basic a distinction between planning and design as you will find. So let us proceed to the problem.

A typical fleet maintenance facility ranges anywhere from about 5,000 square feet to several hundred thousand square feet, depending on the size of the city or a company’s fleet. The case study in this article is based on a community of about 25,000 population. The main purpose of the fleet maintenance facility is, of course, to provide an adequate number of maintenance bays along with support areas such as maintenance shops, central lubrication systems, parts rooms, general storage areas, supervisor’s office, break rooms, restrooms, lockers and mechanical space. This list is by no means all-inclusive. The objective of the planning process is to clearly identify exactly what functions are required. That begins with the first step in the planning/programming process: data gathering.

There are several important types of information needed to begin programming a fleet maintenance facility. First, how many and what types of vehicles are in the fleet (e.g., 12 automobiles, 15 pickup trucks, 14 heavy dump trucks, etc.)? Second, how many people are currently assigned to the maintenance operations and how many shifts are worked? Third, what maintenance functions are performed in-shop and which ones are contracted out? (See Figure 1 for an example of a data gathering form.)

This information alone will significantly affect the type of maintenance facility to be designed. Obviously, a facility that services all the same type of vehicles will be drastically different than a facility that maintains everything from automobiles to fire trucks.

 

Figure 1: FLEET MAINTENANCE FACILITY DATA
Location: City of Norfolk, Nebraska - Equipment Services Building

1. VEHICLES/EQUIPMENT

Type of Vehicle

Quantity

Length

Height

Weight

Trucks

35

25 ft.

10 ft.

28,000#

Pickups - Vans

37

18 ft.

61/2 ft.

3/4 ton

Cars

22

18 ft.

51/2 ft.

3,000#

Heavy Equipment

14

28 ft.

12 ft.

23,000#

Tractors

9

13 ft.

91/2 ft.

8,500#

Miscellaneous
Equipment

60

 
 
 

TOTAL

177

 
 
 

2. PERSONNEL

Category

Shift A

Shift B

Shift C

Supervisor

1

N/A

N/A

Foremen

0

N/A

N/A

Mechanics

3

N/A

N/A

Servicemen

1

N/A

N/A

Clerical

0

N/A

N/A

3. FLEET MAINTENANCE FUNCTIONS

Functions

Performed In-Shop

Contracted Out

Fueling

100%

0%

Washing

100%

0%

New Vehicle Preparation

100%

0%

Lube and Oil Changes

100%

0%

Unit Repair (Alternators,
Generators etc.)

95%

5%

Wheel Alignment

0%

100%

Front End Alignment

0%

100%

Brake Work

100%

0%

Tire Work

0%

100%

Welding Repairs

100%

0%

Collision Repair, Frame
and Body Work

50%

50%

Painting

60%

40%

Transmission and Axle

95%

5%

Hydraulic System Repair

100%

0%

Radio Service

5%

95%

Diagnostics

90%

5%

Small Engine Repair

100%

0%

 

An incredible amount of equipment is housed in a fleet maintenance facility. In many cases however, the municipality or company has never conducted an equipment inventory. This step is a must in the planning of a fleet maintenance operation. Almost all new or expanded facilities will reuse some or all of the fixed and movable vehicle maintenance equipment. A detailed inventory will include a description of the equipment, manufacturer, physical dimensions, utility connections and a photograph of the piece of equipment. (See Figure 2 for a sample equipment inventory form.) When this equipment information is all tabulated the programmer and the owner can sit down and objectively determine if a piece of equipment should be relocated, discarded or replaced. This information is essential for the planner/programmer for it can dramatically affectthe size and configuration of the spaces in the proposed facility.

Site data, or site selection, is another key component in the data gathering phase. If you are selecting an entirely new site, the process of gathering information to make an informed decision can be very demanding, and the subject is worthy of a separate article in Petroleum Equipment & Technology at a later date.

In many cases, however, the site is already determined, or someone may be adding space on an existing fleet maintenance facility site. Information needed includes accurate topographic information (including location and sizing of all underground utilities and other improvements, location of easements, right-of-ways, zoning setbacks and access points), environmental restrictions, soil conditions and other conditions. The planner and owner should review a detailed checklist of the site data during the early stages of the planning/programming process.

 
 

Figure 2

Data analysis involves several key components:

1) a calculation of demand (how many vehicles will be serviced in a year);
2) an analysis of the individual spaces required in the facility; and
3) an analysis of the alternatives available to you in siting the facility.

Calculating the demands for vehicle maintenance, or facility utilization, is an essential part of the planning process. It requires documentation or an estimate by the shop foreman of the number of planned maintenance and breakdown visits per year, and the average service time for each of the different vehicle types. (See Figure 3 for an example of the demand form.) This information provides a good indication of the number of maintenance stalls required and the number of staff required to service the current number of vehicles in the fleet. If you are given the population projections of a municipality, or trends for a company, you can use the data to project the number of maintenance stalls required over the next 5 to 10 years.

Look at the utilization chart (see Figure 3) for an example of this analytical approach to determine maintenance bay needs. The total planned and breakdown maintenance visits per year totals 3,620 hours or 452 workdays. This is the time spent on maintaining or repairing the 117 vehicles in the Norfolk City fleet. It does not include the time spent on maintaining and repairing the 60 pieces of miscellaneous equipment, such as mowers and other small engine equipment.

Assuming that mechanics work a 40-hour week with a utilization of 75 percent (vacations, sick leave, holidays, nonbillable time), the annual hours per mechanic available for vehicle maintenance work is 1,560. This figure justifies the need for three full time mechanics, balanced against the 3,620 hours required for maintenance of the Norfolk City fleet (3,620÷1,560 = 2.32). (The difference between 2.32 required personnel and 3.0 actual personnel is justified by the time required to maintain the remaining 60 pieces of small, miscellaneous equipment.)

Figure 3: FLEET MAINTENANCE FACILITY UTILIZATION
Location: City of Norfolk, Nebraska - Equipment Services Building

 

Auto/
Van

Small
Trucks

Med.
Trucks

Heavy
Trucks

Heavy
Equip.

Misc.
Veh.

Number of Vehicles

25

34

31

4

14

9

Number of Planned Maintenance Visits Per
Year (Total Per Category)

100

129

62

8

42

21

Average Duration
of P.M. Visit

4 hr.

5 hr.

7 hr.

8 hr.

9 hr.

9 hr.

Number of Breakdown Maintenance Visits Per
Year (Total by Category)

103

39

70

20

84

189

Average Duration of Breakdown
Maintenance Visit

3 hr.

2 hr.

2 hr.

4 hr.

4 hr.

3hr.

The City of Norfolk is projected to grow moderately over the next 10 years, and its growth would justify the need for additional vehicles and one additional mechanic. Therefore, the facility is being planned as a four-mechanic facility.

On a single shift operation, it is common practice to provide two maintenance bays per mechanic. This provides the opportunity to stage one vehicle while the other is being serviced, or if delivery of parts delays one vehicle, the mechanic can work on he other one. This arrangement maximizes the mechanic’s efficiency and keeps more vehicles awaiting maintenance out of the weather.

With four mechanics, and based on the usage data, we analyzed that the facility would need a minimum of six maintenance stalls plus three preventive maintenance stalls. We also recommended that the bays be drive-throughs with two stalls per bay because this facility will service numerous pieces of large equipment and fire trucks; and the drive-through buys will facilitate maneuvering of vehicles.

Once we determined the number of maintenance and service stalls required, it was very tempting to immediately begin to design the facility. But there is an important step to take here that will save the designer and the facility user a lot of grief down the road: the program space analysis form. This is a standard form that is filled out for each and the activity to take place, the goals and objectives of the space, the desired adjacencies to other functions, the special building and utility requirements that are to be provided in the space and a listing of all the equipment that will be housed in the space. (See Figure 4 for a sample of the space analysis form.) Each form is accompanied by a diagrammatic floor plan sketch that depicts, to scale, the desired space configuration, and the equipment and utility services in the space. (See Figure 5.)

Figure 4: PROGRAM SPACE ANALYSIS
(Excerpt of original form)
Norfolk Equipment Services Building—Vehicle Maintenance Facility Data

Activity Area Code No.

Activity Name

Number of Occupant(s) Per Space

Number of Spaces Required

Area Per Space (NASF)

Total (NASF)

1.01

Maintenance Bays

1

6

22x37.3

4,950

Description:

• Maintenance and repair of vehicles and equipment

• Storage of large equipment in inclement weather

Goals:

• Flexibility for routine and special maintenance operations

• Two-speed, 3 ton bridge crane
• Drive-thru bays - 2 stalls per bay

Functional
Relationships:

• Adjacent to P.M. and fabrication
• Adjacent to parts

• Adjacent to supervisor's office

Special Architectural & Utility Requirements

Characteristics

Mechanical and Electrical

Ceiling Height

120' clear1

Nat. Lighting

diffused preferable

Floor Finish

sealed concrete-impenetrable to grease and oil

Artif. Light.

metal halide

Wall Finish

paint-washable finish

Services

110V and 480V

Ceiling Treat.

paint

Security

lockable doors

Acoustic Treat.

N/A

Fire Protect.

sprinklered

Special Req.

14'W x 16'H - high lift overhead doors

Special Req.

compressed air; hose bibs; carbon monoxide alarm

Description of Fixed Equipment Requirements

Existing Equipment to be Reused (Examples):

New Equipment (Examples):

No.

Description (include size if applicable)No.

Description (include size if applicable)

1

Generator-alternator starter tester (bench mount)

1

3-ton, 2-speed bridge crane over two bays, motordriven trolley, electric wire rope hoist.

2

Metal workbench - 36"W x 60"L x 34"H

 

Hook height minimum of 14'.

1

Metal workbench - 36"W x 144"L x 34"H

2

12,000#, 2-post vehicle hoists

1

Parts cleaner - 36"W x 28"D x 36"H

1

Oil dump to 550-gallon storage tank

1

Parts cleaner - 20"D x 36"H

2 sets

Lube reels • motor oil 10W/30W • anti freeze
motor oil 15W/40W • ATF
hydraulic oil • air

Description of Fixed Equipment Requirements

Existing Equipment to be Reused (Examples)

No.

Description (include size if applicable)

No.

Description (include size if applicable)

1

Defueling cart 24"W x 24"D x 58"H

1

Engine hoist 40"W x 66"D x 72"H

1

Miller AEAD 200LE welder 64"W x 126D x 78"H

1

Engine stand 34"W x 44"D x 39"H

4 pr.

1-1/2T and 5T jackstands

1

Axle jack 10"W x 54"D x 10"H

4

Floor jacks 2-2T, 1-4T and 1-7T

1

Lincoln engine jack 40"W x 40"D x 39"H

1

Walker 7T bumper jack

1

Wheel dolly 38"W x 44"D x 34"H

1

Transmission jack

2

Craftsman tool chests 44"W x 20"D x 52"H

 

Figure 5: Example of a floor plan sketch.

This approach to planning/programming for the Norfolk facility resulted in a building program that had the following functional components:

Activity Name

Net Square Feet

Maintenance Bays

4,950

Preventive Maintenance Bays

2,475

Welding Bay

825

Wash Bay

1,650

Maintenance Shop

396

Central Lubrication/
Flammable Storage Room

190

Parts Room

620

General Storage

650

Supervisor’s Office

150

Break Room

225

Restrooms/Lockers

330

Mechanical Room

400

Total Net Assignable Area
Circulation, Walls, Structure

12,861
1,286

TOTAL GROSS AREA (square feet)

14,147

Will the site be able to accommodate maneuvering and stacking all the vehicles that will be serviced at this site? This is the major criteria in analyzing the site for a proposed fleet maintenance facility.   

Given the proposed facility square footage determined in the preceding space analysis phase, the planner/programmer should determine if the site area is adequate for the proposed improvements. This phase usually involves studying alternative site layouts to assure that circulation, access and vehicle storage space can be accommodated.   

One of the main objectives of planning/programming is to balance the proposed scope and quality of the project with the owner’s budget. Too often, the final design phase commences with an intuitive feeling that the project can somehow be built for the amount the client has allotted. This frequently results in many modifications to the design to bring it within the budget; time is lost and often, the design is compromised. Project budgeting in the planning phase looks at the entire project budget, not just the cost of construction. Given a definitive program of space and equipment needs, the planner can accurately budget the project with the client, and make necessary changes in the proposed project scope or intended quality well before the project moves into the design stage.

The preliminary budget accounts for construction cost, equipment costs, land acquisition, fees, administrative costs, contingency and a cost escalation formula. The budget of the Norfolk Equipment Services Building begins with a construction cost estimate that is based on (1) a building systems approach taken from the data and (2) assumptions developed in the planning process. The building systems approach allows the planner to make some broad modifications to the intended materials and systems well before the design begins. (See Figure 6 for the format for the programming budget.)

The planning/programing document is, first and foremost, a guide for the designer. As indicated earlier, it clearly defines the problems that the designer will solve, and it serves as a checklist during the design process to ensure that all functions, equipment and building systems are accounted for. The document can also serve the purpose of a financial pro-forma. When the lender or bonding agent wants to substantiate the need for the project, or understand where the money will be spent, the planning/programming document will answer those questions. It can also be used as an equipment procurement list. Since a detailed equipment inventory is included in the document and the equipment items are itemized for each functional space, that list can serve as the equipment checklist.

Many times the planning/programming process organizes vital information about a fleet maintenance operation that has never before been documented. It can serve as a catalyst for improving the efficiency and organization of a fleet maintenance program.

“You can’t be lost as long as you don’t know where you’re supposed to be.” Murphy

Don’t be caught by Murphy’s Law of Directions. Good buildings, whether they are fleet maintenance facilities or corporate office buildings, don’t just happen. They are planned. The myth of designing a great building on the back of a napkin is the stuff of Hollywood. Planning, it must be understood, is a process: a process that involves significant client involvement, a process that promotes effective communications; and a process that uses qualitative and quantitative information to produce objective design criteria.

In the next issue we will examine the process of facility design using the programmatic information presented in this article.

Figure 6: PRELIMINARY PROJECT BUDGET
City of Norfolk, Nebraska–Equipment Serivces Building
Assumptions: Building area of 14,147 s.f.,
masonry walls, steel bar joist and metal roof deck construction

Item No.

Budget Item

Est. Cost

Subtotals

1.

Construction

 

 

1a.

Site Development

$86,000

 

1b.

Foundations

$70,500

 

1c.

Substructure

$35,600

 

1d.

Superstructure

$26,400

 

1e.

Exterior Closure

$95,800

 

1f.

Roofing

$48,900

 

1g.

Interior Construction

$42,400

 

1h.

Mechanical

$185,000

 

1i.

Electrical

$65,300

 

 

SUBTOTAL

 

$655,900

2.

Special Construction

 

 

2a.

Air Compressor

$5,000

 

2b.

3 - 12,000 lb. Hoists

$24,000

 

2c.

1 - 54,000 lb. Hoist

$16,000

 

2d.

Lubrication Equipment

$22,000

 

2e.

Crane Rail and Hoists

$40,000

 

 

SUBTOTAL

 

$107,000

3.

Overhead & Profit (15%)

 

$114,000

4.

A/E Fees (7.5%)

 

$64,500

5.

Moveable Equipment

 

$10,000

6.

Administrative Costs

 

$8,700

7.

Contingency (5% Const. Cost)

 

$43,900

 

TOTAL PROJECT BUDGET

 

$1,004,400

William (Larry) Jacobsen AIA, FCSI provides architecture and engineering planning expertise for The Schemmer Associates Inc., where he is a principal.